Corporate Partners

Many thanks to our Corporate Partners for supporting the WTS-OC Chapter!

The Corporate Partner Program details and a complete list of benefits can be found by clicking on the link below: 

Questions?

Lauren Uyeno, Corporate Partners Chair

Lauren.Uyeno@stantec.com

Thank you to our Corporate Partners!

To learn more about some of our Corporate Partners, click the button below. 


To visit our Corporate Partners' websites, click on each of their logos. 

Diamond

Nossaman LLP Circle Logo Final.png
HDR.png
RebuildSocal_New-Logo-F_Color (1).png
Jacobs_logo_rgb_black.jpg
Southern_California_Edison_logo.png
parsons_logo_color.png
exp_logo.jpg

Platinum

TYLI_tagline_vector_large.png

Gold

Psomas.png
MT_Logo.jpg
Moffat Nichol.jpg
01 Hill Logo Full Color Standard RGB.png
stantec_black_pos_rgb.jpg

Silver

TranSystems Logo.png
Insight 2020 Logo.jpg
Twining_color_2kpx.png
Kleinfelder.png
cp-logo-2019.png
Dewberry Logo.jpeg
ICF-logo-black.png

Bronze

Ghirardelli.jpg.png
Civil Works.jpg
Monument.jpeg
Paragon Partners.jpg

Corporate Partner Highlight 

Nossaman LLP Circle Logo Final.png
Nossaman1.jpg
The Santa Fe Depot in San Bernardino California
Nossaman2.jpg
Pedestrian Railway Crossing at San Bernardino downtown
San Bernardino County Transportation Authority (SBCTA)

Nossaman’s Eminent Domain & Valuation Group has been assisting SBCTA with right-of-way acquisition/eminent domain services continuously since 2010. SBCTA has been one of our key agency partners in eminent domain, and we are proud to have partnered with SBCTA on several major right-of-way projects, including the Downtown San Bernardino Passenger Rail. This project included a one-mile extension of the existing Metrolink service from the historic San Bernardino Depot to a new station being constructed in conjunction with San Bernardino’s Transit Center. Nossaman provided substantial pre-condemnation guidance to reduce the number of required properties, and worked closely with the project engineers during the project’s design process to minimize the agency’s exposure to damages claims. We secured timely possession of all necessary right-of-way, allowing project construction to commence without right-of-way delays, and successfully resolved all but one acquisition without the need for trial. In the one case that went to trial, Nossaman obtained a judgment at exactly our appraised value (approximately ten percent of the owner’s number), before a jury was ever empaneled. In May 2018, the Court of Appeal affirmed that judgment in its entirety.